The Alberta Utilities Commission has approved a 1,494-megawatt power plant that will fuel a proposed hyperscale data centre located on the same site, despite significant community opposition to the project.
The power plant will be located approximately three kilometres east of Calgary’s city limits near the town of Indus in the rural district of Rocky View County.
Construction on the power plant is expected to begin before the end of the year and is forecast to come online in the final quarter of 2027, said the announcement from the AUC.
The power plant is the third such project with an on-site data centre to be approved by the regulator since the province launched its strategy in 2024 to attract investments in the large electricity-thirsty computing facilities.
It is being developed by a subsidiary of Beacon Data Centers, founded in 2023 by New York-based venture capital firm Nadia Partners.
How Danielle Smith’s risky bet on data centres could backfire
The AUC has also approved a 1,864-megawatt power plant and 902-megawatt power plant in Sturgeon County, located in the Industrial Heartland just outside Edmonton.
The larger site will fuel Meta’s $13-billion data centre announced in July. The second project was approved by the AUC last month. It is also being developed by a subsidiary of Beacon Data Centers.
Anthropic is in advanced talks to lease the facility to be powered by the second Sturgeon County plant, The Globe and Mail reported last month.
The Indus project has faced fierce community opposition since the project plan was put before the AUC in December of last year.
In AUC proceedings over August and September, over 20 landowners living close to the site expressed concerns about the project’s environmental and air effects, water use, noise, and the potential impact on agricultural and livestock operations.
Alberta’s data centre policies will help lure projects, power producers say
The developer has also offered homeowners living next to the site substantive sums to sell their land, The Globe has reported.
The Indus project has also changed in scope since the general site plan was approved by the municipality in July 2025. At the time, the proposal did not include a power plant. The data centre was projected to be primarily powered by the provincial grid. Plans changed after the province restricted grid connections for data centres and directed developers to build their own power supply, but the site permitting still applied.
Rocky View County cannot now oppose the power plant because the AUC’s decision overrules the municipality. It may apply municipal conditions, as long as they do not conflict with the AUC’s requirements.
The AUC’s decision Tuesday extends only to the power plant. The on-site data centre is still subject to municipal approval.
The AUC approved the Indus power plant one day before the province is set to announce new guidelines on data centres. The Minister of Technology and Innovation, Nate Glubish, will join other provincial ministers at announcement in downtown Edmonton on Wednesday afternoon to unveil the new restrictions.
The AUC is in the process of reviewing three more power plants with associated data centres, according to a statement provided to The Globe last week. Only one of these proposals – located in Northern Sunrise County – is for a power plant over 100 megawatts.
With reports from Matthew Scace
More Stories
Massive Deutsche Bank leak prompts investigation by data watchdog
What to know about Anthropic’s blockbuster IPO
Fed officials focus on inflation risks in October as some see need for further rate hikes